This project needs an independent review.

CMP’s Greater Portland Transmission Upgrades would affect Cumberland, Falmouth, Portland, Westbrook and Yarmouth. CMP estimates Phase 1 alone at $547 million. In the case record, these groups are questioning its proposal:

Maine Office of the Public Advocate

Asks the Commission to “direct an independent review” of CMP’s forecast. Item 210 ↗

City of Portland

Questions CMP’s need and its route through dense neighborhoods. Item 209 ↗

Town of Falmouth

Unanimously opposed the project as submitted. Item 168 ↗

Conservation Law Foundation

Backed the request to test CMP’s claimed need first. Item 142 ↗

Town of Cumberland

Resolved on Nov. 9 to oppose the project as submitted. Council resolution ↗

Why it needs a review
Aerial view of Falmouth’s school campus, with the approximate CMP easement drawn in yellow alongside the fields and the Merrill property outlined in red.The approximate CMP easement (yellow) beside Falmouth’s school campus and the Merrill property (red) for campus expansion. Town of Falmouth testimony, Exhibit D, Item 197 ↗

Understand the impacts.

2,200+residential addresses within 1,000 feet
$547MCMP’s Phase 1 estimate, paid by CMP customers
110 ftsteel monopoles, up to about 110 feet tall

Private property and overburdened rights-of-way, Falmouth’s school campus, the degradation of our public and communal spaces, and the environmental impacts. High-voltage transmission lines don’t belong in residential neighborhoods.

See the impactsHealth & safety
CUMBERLANDFALMOUTHPORTLANDWESTBROOKYARMOUTHApproximate route, based on CMP’s filings

Add your voice to the record.

The Commission decides on what’s in the record. A public comment takes five minutes, and you don’t need a lawyer or to be a party.

File a public comment ↗All dates and ways to help

Show up in person

Nov9
CMP open house, Westbrook6–8pm, 426 Bridge St.
Nov9
Cumberland Town Council7pm, public comment
Nov10
ARI session + CMP open house, Portland4pm and 6pm, Presumpscot Elementary
Nov12
CMP open house, Cumberland6pm, Town Hall
Nov16
Portland City Council5pm, City Hall, public comment
Nov18
Portland Sustainability and TransportationTime on the posted agenda
Nov19
Yarmouth Town Council7pm
Dec10
Technical conference, Hallowell9am, 26 Katherine Dr, or streamed

CMP keeps changing its story on why this project is needed.

Landowners on the route, the Public Advocate, the Conservation Law Foundation and Falmouth pushed back on CMP’s forecast. Then CMP changed its story.

BEFORE · Sept. 2025 · What CMP told the Commission

The need is driven by forecast load growth and aging equipment.

CMP’s petition, p. 16 ↗

AFTER · Oct. 21, 2026 · What CMP told Portland councilors

The need is here now, not in a future forecast.

City of Portland meeting ↗

Our view: failing equipment and forecast electricity use are two different needs. CMP keeps blending them.

Which is it? →

See where it runs

CMP’s Phase 1 route, street by street.

The existing corridor, where the new and rebuilt lines would run inside it, and how wide the clearing would be. Zoom in to find your street, and click any line for details.

Map key

    Illustrative. Line positions are drawn from CMP’s cross-sections and public line data; they are not a survey and not a prediction for any one property. The Westbrook right-of-way width is assumed at 100 ft because CMP’s petition does not give one. The Portland rail-corridor alignment is approximated from CMP’s public images. Sources: CMP petition, pp. 29–30 and 37 ↗; CMP data responses AP01-001-018, EXM-004-002, ODR-001, ACAUS-001-001, AP01-001-013, MAS-001-008 (Data Requests tab ↗). Also see CMP’s project map ↗.

    Go deeper

    Why an Independent Review

    CMP earns a return on what it builds. The Public Advocate, Portland, Falmouth, Cumberland and the Conservation Law Foundation are all questioning the need.

    See why →

    The Case: CMP’s Proposal and Alternative Solutions

    What CMP wants to build, the routes it set aside, and why the non-wires review starts from CMP’s own need.

    Read the case →

    Understand the Impacts

    2,200+residential addresses within 1,000 feet
    $547MCMP’s Phase 1 estimate, paid by CMP customers
    Phase 2CMP’s petition: to be filed by Dec. 31, 2026

    Private property and overburdened rights-of-way, Falmouth’s school campus, the degradation of our public and communal spaces, and the environmental impacts.

    See the impacts →

    Take Action

    File a public comment, come to the next meeting, or document your property.

    What you can do this week →

    Resources

    Who we are, guides, and the filings behind everything on this site.

    Find documents →
    Health & safetyEMF, herbicides and wildfire: what we know, and what we’re asking CMP to share.Read more →

    Stand with your neighbors.

    We’re pro-electrification. Portland should get the power it needs. We’re not opposed to CMP as a matter of principle; we’re asking for more from a public utility.

    Did you hear about this project from CMP, or from somewhere else?

    One click helps us document notice for the state case.

    Thanks, your answer’s recorded.

    Got 60 more seconds? Take the short survey →

    Alliance for Responsible Infrastructure · contact@ariforme.org · Docket No. 2025-00276