Understand the impacts.

What CMP’s Phase 1 would mean for private property, our schools, the places we share, the environment and what we all pay.

2,200+residential addresses within 1,000 feet of the project
110 ftsteel monopoles, up to about 110 feet tall
100 ftfull width of right-of-way CMP says it will clear, plus hazard trees 15–20 feet beyond the edge
$547MCMP’s Phase 1 estimate, paid by CMP customers

And this is only Phase 1. CMP says a Phase 2 filing will follow by Dec. 31, 2026. Petition, p. 8 ↗

Private propertySchool campusShared spacesEnvironmentHealth & safetyCost

Private property and rights-of-way

A corridor of wooden poles would become a high-voltage steel line.

These easements date from 1948–1954. In Falmouth, the corridor holds wooden poles 50 to 75 feet tall. CMP would add steel monopoles up to about 110 feet and clear it edge to edge. We believe that overburdens these rights-of-way, and neighbors should not carry the cost.

−15% to −34%

value impact on nearby properties in the comparable studies reviewed in Northern Pass testimony. Directional, not an appraisal.

75 ft

The Town of Falmouth reports “some homes that are within 75 feet of the existing power lines.”

0

property-value criteria in the siting procedure CMP filed in this case.

What CMP saysIt already holds “sufficient easement and property rights.” It also “cannot currently quantify the number of structures or abutters affected.”

The Town reports the Cumberland County Assessor “has stated that there will be an adverse impact on property values.” Town of Falmouth testimony, Item 197 ↗ · Northern Pass testimony ↗ · Registry of Deeds ↗ · AP01-001-018, EXM-004-004, EXM-004-001 Att. 1: case page, Data Requests tab ↗

Conceptual diagram of a 115 kV steel monopole beside a shorter separate 34.5 kV pole, with a person shown for scale.
Illustration by the intervenors’ technical expert, from the pole types and heights in CMP’s petition. Not to scale for any specific property.

Falmouth’s school campus

One shared campus, students ages 3 to 22.

Aerial view of Falmouth’s school campus, with the approximate CMP easement drawn in yellow alongside the fields and the Merrill property outlined in red.
The approximate CMP easement (yellow), the school campus, and the Merrill property (red) for campus expansion. Town of Falmouth testimony, Exhibit D.
70 ft

from the existing lines to the outdoor baseball fields, by the Town’s estimate.

430 ft

from the existing lines to the high school building, by the Town’s estimate.

“The project, as proposed, places an unacceptable burden on our school community.”

Falmouth Public Schools and School Board, to the Commission. They ask that CMP be required to reroute the lines away from the campus.

What CMP saysIt “has not performed a project-specific EMF assessment for the Phase 1 Project.”

Town of Falmouth testimony, Item 197 ↗, Exhibits C, D, E · AP01-001-009: case page, Data Requests tab ↗

Public and communal spaces

The places we all share.

CMP’s corridor crosses conserved land, trails and rivers in town after town. In Falmouth, the Town says these places are “used by thousands of residents and visitors year-round.”

CUMBERLANDFALMOUTHPORTLANDWESTBROOKYARMOUTH12345678910111213141516
CMP’s new 115 kV line (thick) and rebuilt lines (thin)   Conserved land and historic places   Trails. Approximate route, based on CMP’s filings.

Falmouth

  • 1McCrann Preserve
  • 2Woods Road Community Forest
  • 3River Point Conservation Area
  • 4Pleasant Hill Preserve
  • 5The Ledges Preserve
  • 6Stormy Brook Preserve
  • 7River’s Edge

Portland

  • 8Presumpscot River Preserve
  • 9Presumpscot River Trails
  • 10Sebago to the Sea Trail
  • 11Virginia Woods
  • 12Evergreen Cemetery (National Register)

Westbrook

  • 13Stroudwater River
  • 14Stroudwater Trail
  • 15Lovejoy Farm conservation land, about 130 feet from the line

Cumberland

  • 16East Coast Greenway

Yarmouth

Elm Street substation work. State data shows no conserved land or trail crossed by the line.

At River Point, used for millennia as a campsite by Native Americans, work “would likely disturb and harm thousands of years of human history.”

Town of Falmouth testimony, Item 197 ↗ · Alliance review of State of Maine conserved lands, National Register and public trail data along CMP’s proposed route.

Environment

Streams, habitat and rare wildlife.

CUMBERLANDFALMOUTHPORTLANDWESTBROOKYARMOUTH123456789
Named rivers and streams the route crosses (blue lines) and large mapped wetlands it crosses (blue areas). Approximate route, based on CMP’s filings.
  • 1Presumpscot River
  • 2Piscataqua River
  • 3East Branch Piscataqua River
  • 4Mill Creek
  • 5Meader Brook
  • 6Johnson Branch
  • 7Chenery Brook
  • 8Minnow Brook
  • 9Stroudwater River
34

large mapped wetlands crossed by the route.

3

known rare, threatened or endangered species occurrences in habitat the easement crosses in Falmouth: Least Bittern, Spotted Turtle and Wood Turtle.

The easement crosses several streams, creeks and the Presumpscot River. The Falmouth Land Trust warns that utility corridors often spread invasive species into protected areas.

What CMP saysIt “has not developed a restoration, replanting, or screening plan.”

Town of Falmouth testimony, Item 197 ↗ · AP01-001-014: case page, Data Requests tab ↗ · Streams and wetlands: Alliance review of public water and wetland maps along CMP’s proposed route.

Health and safety

Questions CMP hasn’t answered.

Herbicides

CMP’s plan filed with the state ↗ uses herbicide spraying on a roughly four-to-five-year cycle.

The plan that would govern this corridor was filed only as a confidential attachment, so the neighbors and schools next to it can’t review it.

EMF

CMP “has not performed a project-specific EMF assessment.”

The International Agency for Research on Cancer classified this type of exposure as a possible carcinogen in 2002. No causal link has been confirmed. Why hasn’t CMP shared the data for this line?

Wildfire

Maine’s climate scientists project “more than a doubling of fire probability in the state.”

Overhead lines can start fires when hardware wears out or trees fall into the wires.

We’re asking for a setback of 300 feet for above-ground high-voltage lines and 50 feet underground.

AP01-001-009, MAS-001-012: case page, Data Requests tab ↗ · What we know, and our sources ↗

Cost

And CMP customers pay for it.

$547M

CMP’s estimate for Phase 1 alone.

9.57%

return on equity in CMP’s own cost model. CMP earns a return on what it builds.

What CMP says“None of the cost for the Phase 1 or Phase 2 project elements can be regionally socialized.”

CMP’s model also includes no operations and maintenance cost. Falmouth Public Schools has asked the Commission to require CMP to quantify the rate impact.

Petition, p. 43 ↗ · Town of Falmouth testimony, Item 197 ↗, Exhibit E · ODR-001-010 Att. 1: case page, Data Requests tab ↗

Put your impact on the record.

Document your property, estimate the potential value impact, or file a public comment.

Document your propertyFile a public comment ↗

Stand with your neighbors.

Alliance for Responsible Infrastructure · contact@ariforme.org · Docket No. 2025-00276
Nov9
CMP open house, Westbrook6–8pm, 426 Bridge St.
Nov9
Cumberland Town Council7pm, public comment
Nov10
ARI session + CMP open house, Portland4pm and 6pm, Presumpscot Elementary
Nov12
CMP open house, Cumberland6pm, Town Hall
Nov16
Portland City Council5pm, City Hall, public comment
Nov18
Portland Sustainability and TransportationTime on the posted agenda
Nov19
Yarmouth Town Council7pm
Dec10
Technical conference, Hallowell9am, 26 Katherine Dr, or streamed
0
Skip to Content
ARI
STOP the CMP Line
ARI's position of safety issues
ARI
STOP the CMP Line
ARI's position of safety issues
STOP the CMP Line
ARI's position of safety issues