The case: CMP’s proposal and alternative solutions.

We all want reliable power. CMP has to show this project is the right way to get it.

What CMP proposesThe mapThe real needThe alternativesHow CMP picks a routeNon-wires optionsWhat CMP saysWhere the case stands

What CMP proposes

CMP’s $547 million first phase.

  • A new 115 kV line through Cumberland, Falmouth and Portland, on steel poles up to about 110 feet tall.
  • Rebuilt lines in Westbrook.
  • Substation work: expanding Raven Farm and East Deering, a new Bayside substation, and removing Elm Street in Yarmouth.
  • About $547 million, CMP’s estimate, with a stated range of −25% to +50%. A Phase 2 filing would follow.

CMP’s first phase is focused on Portland, and its case leans on a prediction of how much total electricity the area will use. That prediction comes from a regional forecast since revised down, and the Public Advocate has raised concerns that it’s overestimated. Towns north of Portland would get little to no benefit while bearing the harm.

CMP petition, pp. 8, 15, 29–30 ↗ · Item 141 ↗

Rendering of a tall gray steel monopole carrying transmission lines beside a rail corridor, towering over the surrounding trees.
ILLUSTRATION · CMP petition, Figure 9 (S263).

See it on the map

Where CMP would build.

The existing corridor, where the new and rebuilt lines would run inside it, and how wide the clearing would be. Zoom in to find your street, and click any line for details.

Map key

    Illustrative. Line positions are drawn from CMP’s cross-sections and public line data; they are not a survey and not a prediction for any one property. The Westbrook right-of-way width is assumed at 100 ft because CMP’s petition does not give one. The Portland rail-corridor alignment is approximated from CMP’s public images. Sources: CMP petition, pp. 29–30 and 37 ↗; CMP data responses AP01-001-018, EXM-004-002, ODR-001, ACAUS-001-001, AP01-001-013, MAS-001-008 (Data Requests tab ↗). Also see CMP’s project map ↗.

    What the real need is

    Reliability.

    Reliability and load aren’t the same thing. Reliability, as most people mean it, is equipment that works and doesn’t fail. Load is the total electricity an area uses, and a forecast of more load is what calls for a bigger system. CMP folds the two together: its petition says the needs are “driven by forecasted load growth in the area and asset condition.” If the forecast is too high, part of that need goes away.

    The needs CMP now points to are reliability problems: equipment that wore out and failed.

    One worn-out part at the Elm Street substation knocked out power to 28,000 customers on Oct. 9. An 80-year-old line failed in 2023. Fix them. That’s upkeep, and it doesn’t take a new 115 kV line through people’s backyards. CMP’s own plan prices rebuilding the old lines and building the new 115 kV line as separate jobs.

    CMP makes more money the more it builds.

    It earns a return on every dollar it spends on projects like this one. Bigger project, bigger payday. That’s why someone independent has to check the need first.

    CMP at Portland’s Sustainability and Transportation Committee, Oct. 21, 2026 ↗ (outages) · CMP petition, p. 1 ↗ (need) · CMP petition, Table 1, Cost Summary ↗ (separate line items) · ODR-001-010 Att. 1: case page, Data Requests tab ↗

    The alternatives

    CMP says it looked at alternatives. Its answers keep changing.

    What the record shows: CMP has given at least four different bases for the cost of undergrounding. Its comparisons count construction only, not the net economic impact of each option.

    Below: CMP’s own answers, and when it gave them. Text in quotation marks is CMP’s wording; the rest summarizes CMP’s own figures.

    What CMP said…
    …to the Commission
    …to Falmouth, Oct. 13
    …to Portland councilors, Oct. 21
    …to Falmouth, Oct. 30
    I-295 corridor cost, compared with CMP’s route
    “more than six times”
    “more than six times”
    would “add at least $130 million”
    about 3.3 times
    Rail corridor cost, compared with CMP’s route
    “approximately two times”
    —
    would “add around $90 million”
    about 2.5 times
    Why rail was set aside
    MaineDOT said the corridor was “not acceptable”
    —
    Cost, and it would “impact many additional properties and landowners”
    “primarily” cost; still “coordinating with MaineDOT”
    Price of the original design and the redesign
    —
    —
    —
    Same price, though the original needed about $10 million more in right-of-way

    What CMP isn’t saying: its parent company’s procedure favors whatever carries less “cost and risk to the project” itself. The net economic impact on the community is never measured. Why an independent review matters →

    The City of Portland, in its testimony: CMP’s petition “does not adequately explain why the Project could not continue to follow the railroad corridor.”

    Petition, p. 48 ↗ · Item 174 ↗ · City of Portland meeting, Oct. 21 ↗ · Item 238, pp. 7–8 ↗ · Item 209 ↗ · MAS-001-009; Iberdrola USA procedure (2015), filed by CMP as EXM-004-001 Att. 1, pp. 6, 8–16: case page, Data Requests tab ↗

    How CMP picks a route

    CMP’s siting procedure starts with the land it already has.

    Starts here

    Real Estate’s “records that determine what IUSA owns for property.” IUSA is Iberdrola USA, CMP’s parent company at the time.

    Protects

    The project, not the neighbors. It favors whatever carries less “cost and risk to the project.” The “real estate costs” it works to minimize are what CMP pays for land rights. Neighbors’ property values are not a factor.

    Leaves out

    The criteria include parcels, buildings and permits. Nothing measures the net economic impact on the community.

    Less destructive options deserve a real look:

    I-295 corridorRail corridorUndergroundingSubmarine line

    Why an independent review matters →

    Iberdrola USA, Project Options Analysis, filed by CMP as EXM-004-001 Att. 1, pp. 6, 8–16: case page, Data Requests tab ↗

    Non-wires alternatives

    The alternatives review starts from CMP’s own need.

    Maine law requires a look at batteries, local generation and demand management. But the reviewer tests them against the need CMP identified, not whether that need is right.

    “They take the needs the company identified at face value.”

    Public Advocate Heather Sanborn, on the non-wires review, Oct. 21, 2026. Her office’s expert says that review rests on inputs “that have since changed.”

    It has worked elsewhere, and in Maine.

    Brooklyn–Queens, N.Y.

    A $1B+ substation deferred

    Con Edison paired efficiency, demand response and batteries with smaller fixes, and earned a return on the program.

    Nantucket, Mass.

    A third undersea cable deferred

    National Grid installed a 6 MW battery and an on-island generator.

    Provincetown, Mass.

    A 13-mile line avoided

    Eversource built a 25 MW battery instead of a new line through the Cape Cod National Seashore.

    Vermont

    110 MW from customer batteries

    Green Mountain Power calls on leased home batteries at peak.

    Boothbay, Maine

    An $18M rebuild avoided

    Local solar, batteries and efficiency “met reliability needs in the pilot area for less.”

    Maine, 2025

    237 MW of batteries

    All owned by independent producers. None by CMP, which earns no return on them.

    35-A M.R.S. § 3132(2-D) ↗ · Item 141, p. 5 ↗ · Item 210 ↗ · City meeting ↗ · NY PSC Case 14-E-0302; Energy-Storage.news; Utility Dive, Apr. 8, 2019; Electrek, July 28, 2026; Boothbay pilot Recommended Decision (2016); EIA.

    Why we’re opposing it as proposed

    Eight things CMP says, and what the record shows.

    Each line below is a claim CMP makes for this project. Click or tap the + to see what the record shows.

    “This project is urgently needed to keep the lights on in Greater Portland.”
    CMP's need rests on a forecast now being questioned in the case record. In public comments filed Sept 28 (Item 141), the Office of the Public Advocate wrote that several of CMP's forecasting practices “raise concerns that the Portland area forecast of load is overestimated, potentially leading to unneeded capital investment.” CMP built its study on a 2024 regional forecast that later forecasts have revised downward, and its own witnesses acknowledged some loads “might be” double counted (Technical conference, Item 131; see also OPA, Item 141 at 4). Keeping the lights on is about equipment that works. A forecast of how much total electricity people will use is a separate question, and CMP’s case depends on both. Independently verifying the need is essential before anything gets built.
    “There's no real alternative to this version of the project.”
    Maine law requires the evaluation of non-wires alternatives such as battery storage and distributed generation (35-A M.R.S. § 3132(2-D); see OPA comments, Item 141 at 5), but the current process only tests whether an alternative can support the need CMP identifies, not whether that need is accurate. Verifying the need could open the door to less destructive solutions, including alternative wire solutions.

    CMP’s case against the alternatives keeps changing. Its petition said an I-295 route would cost “more than six times” the proposed route (petition, p. 48), and CMP repeated that to Falmouth on Oct. 13 (Item 174). Seventeen days later it told Falmouth about 3.3 times (Item 238, p. 7). In September CMP said it dropped the rail corridor because MaineDOT said the corridor was not acceptable (data response MAS-001-009). Now it says the route was “not advanced primarily because of its substantially higher cost,” and that it is still “coordinating with MaineDOT to confirm the information used in its evaluation remains current.” It also puts the same price on its original design and its redesign, though the original needed about $10 million more in right-of-way (Item 238, p. 8). A decision this large should rest on numbers that hold still. The Commission should require an independent look at the alternatives. What CMP isn’t saying: its parent company’s written procedure for choosing a project starts with the land the company already owns and favors whatever carries less “cost and risk to the project” itself (Iberdrola USA, filed by CMP as EXM-004-001 Att. 1, pp. 6, 15). Nothing in it measures the net economic impact on the community. Why an independent review matters →
    “This project is for the public good.”
    We're not against investing in Portland's energy future; meeting growing demand is exactly the job CMP should be doing. But this proposal is destructive. CMP is an investor-owned utility that earns a return on what it builds, so it has every incentive to build big and none to find less expensive or less destructive solutions. That conflict of interest is why this needs independent evaluation.
    “This project serves 200,000 customers in the Greater Portland area.”
    That number describes the whole region, not who benefits. The need behind this project is concentrated in Portland, and it rests on a forecast now being questioned in the record. The towns north of Portland would receive little to no benefit, yet bear the towers, the clearing and the loss of public and private property.
    “This won't have a big impact on landowners.”
    Independent data from comparable cases in New England (the New Hampshire Northern Pass proceeding) found value loss of as much as 34% on the most directly affected properties. In Falmouth, the proposed route could constrain planning for a future middle school site.
    “CMP informed landowners and impacted parties before filing.”
    Most residents learned of the project from our door-to-door canvassing and by word of mouth, not from CMP, and only after CMP had filed.
    “Clearing the right-of-way just means trimming a few trees.”
    CMP's vegetation management plan filed with the Maine Board of Pesticides Control uses herbicide spraying, not just cutting, on a roughly four-to-five-year cycle. Clearing the full width of the right-of-way, plus hazard trees beyond its edge, brings that treatment zone closer to homes, wells, children's play areas, schools and conserved land along this route. Read about the safety concerns we're tracking.
    “This is the best solution to meet Portland's future energy needs.”
    What gets built now will stand for decades in a hotter, stormier Maine, where the state's own scientists project more than a doubling of wildfire probability. Overhead lines are a fire risk: California's deadliest wildfire was started by a 115 kV line, the same voltage proposed here. Undergrounding and other resilient alternatives are safer and deserve a real evaluation. Read about wildfire and climate risk.

    Where the case stands

    The Commission decides in 2027.

    Sept. 2025

    CMP files its petition

    Sept. 2026

    Landowners ask the Commission to test the need first

    Oct. 9

    Commission rules need will be decided in the main case

    Oct. 30

    Intervenor testimony filed

    Dec. 10

    Technical conference on intervenor testimony, Hallowell

    By July 15, 2027

    Commission decides, unless the period is extended

    Procedural Order, Item 155 ↗ · Full case docket ↗

    Tell the Commission what you want it to weigh.

    Your public comment goes straight into the case record.

    File a public comment ↗Why an independent review

    Stand with your neighbors.

    Alliance for Responsible Infrastructure · contact@ariforme.org · Docket No. 2025-00276
    Nov9
    CMP open house, Westbrook6–8pm, 426 Bridge St.
    Nov9
    Cumberland Town Council7pm, public comment
    Nov10
    ARI session + CMP open house, Portland4pm and 6pm, Presumpscot Elementary
    Nov12
    CMP open house, Cumberland6pm, Town Hall
    Nov16
    Portland City Council5pm, City Hall, public comment
    Nov18
    Portland Sustainability and TransportationTime on the posted agenda
    Nov19
    Yarmouth Town Council7pm
    Dec10
    Technical conference, Hallowell9am, 26 Katherine Dr, or streamed
    0
    Skip to Content
    ARI
    STOP the CMP Line
    ARI's position of safety issues
    ARI
    STOP the CMP Line
    ARI's position of safety issues
    STOP the CMP Line
    ARI's position of safety issues